Multi-mode resource constrained multi-project scheduling and resource portfolio problem

Beşikci, Umut and Bilge, Ümit and Ulusoy, Gündüz (2015) Multi-mode resource constrained multi-project scheduling and resource portfolio problem. European Journal of Operational Research, 240 (1). pp. 22-31. ISSN 0377-2217

[thumbnail of This is a RoMEO green journal -- author can archive pre-print (ie pre-refereeing) and post-print (ie final draft post-refereeing)] PDF (This is a RoMEO green journal -- author can archive pre-print (ie pre-refereeing) and post-print (ie final draft post-refereeing))
Besikci,_Bilge,_Ulusoy_EJOR_2014.pdf

Download (363kB)

Abstract

This paper introduces a multi-project problem environment which involves multiple projects with assigned due dates; activities that have alternative resource usage modes; a resource dedication policy that does not allow sharing of resources among projects throughout the planning horizon; and a total budget. Three issues arise when investigating this multi-project environment. First, the total budget should be distributed among different resource types to determine the general resource capacities, which correspond to the total amount for each renewable resource to be dedicated to the projects. With the general resource capacities at hand, the next issue is to determine the amounts of resources to be dedicated to the individual projects. The dedication of resources reduces the scheduling of the projects' activities to a multi-mode resource constrained project scheduling problem (MRCPSP)for each individual project. Finally, the last issue is the ecient solution of the resulting MRCPSPs. In this paper, this multi-project environment is modeled in an integrated fashion and designated as the Resource Portfolio Problem. A two-phase and a monolithic genetic algorithm are proposed as two solution approaches, each of which employs a new improvement move designated as the combinatorial auction for resource portfolio and the combinatorial auction for resource dedication. A computational study using test problems demonstrated the effectiveness of the solution approach proposed. Keywords: Project scheduling, resource portfolio problem, multi-project scheduling, resource dedication, resource preference.
Item Type: Article
Uncontrolled Keywords: Project scheduling, resource portfolio problem, multi-project scheduling, resource dedication, resource preference.
Subjects: T Technology > T Technology (General) > T055.4-60.8 Industrial engineering. Management engineering
Divisions: Faculty of Engineering and Natural Sciences
Faculty of Engineering and Natural Sciences > Academic programs > Manufacturing Systems Eng.
Depositing User: Gündüz Ulusoy
Date Deposited: 28 Aug 2014 10:18
Last Modified: 26 Apr 2022 09:14
URI: https://research.sabanciuniv.edu/id/eprint/24360

Actions (login required)

View Item
View Item