Beşikci, Umut and Bilge, Ümit and Ulusoy, Gündüz (2015) Multi-mode resource constrained multi-project scheduling and resource portfolio problem. European Journal of Operational Research, 240 (1). pp. 22-31. ISSN 0377-2217
PDF (This is a RoMEO green journal -- author can archive pre-print (ie pre-refereeing) and post-print (ie final draft post-refereeing))
Besikci,_Bilge,_Ulusoy_EJOR_2014.pdf
Download (363kB)
Besikci,_Bilge,_Ulusoy_EJOR_2014.pdf
Download (363kB)
Official URL: http://dx.doi.org/10.1016/j.ejor.2014.06.025
Abstract
This paper introduces a multi-project problem environment which involves
multiple projects with assigned due dates; activities that have alternative resource usage modes; a resource dedication policy that does not allow sharing
of resources among projects throughout the planning horizon; and a total
budget. Three issues arise when investigating this multi-project environment.
First, the total budget should be distributed among different resource
types to determine the general resource capacities, which correspond to the
total amount for each renewable resource to be dedicated to the projects.
With the general resource capacities at hand, the next issue is to determine
the amounts of resources to be dedicated to the individual projects. The
dedication of resources reduces the scheduling of the projects' activities to
a multi-mode resource constrained project scheduling problem (MRCPSP)for each individual project. Finally, the last issue is the ecient solution
of the resulting MRCPSPs. In this paper, this multi-project environment is
modeled in an integrated fashion and designated as the Resource Portfolio
Problem. A two-phase and a monolithic genetic algorithm are proposed as
two solution approaches, each of which employs a new improvement move
designated as the combinatorial auction for resource portfolio and the combinatorial auction for resource dedication. A computational study using test
problems demonstrated the effectiveness of the solution approach proposed.
Keywords: Project scheduling, resource portfolio problem, multi-project
scheduling, resource dedication, resource preference.
Item Type: | Article |
---|---|
Uncontrolled Keywords: | Project scheduling, resource portfolio problem, multi-project scheduling, resource dedication, resource preference. |
Subjects: | T Technology > T Technology (General) > T055.4-60.8 Industrial engineering. Management engineering |
Divisions: | Faculty of Engineering and Natural Sciences Faculty of Engineering and Natural Sciences > Academic programs > Manufacturing Systems Eng. |
Depositing User: | Gündüz Ulusoy |
Date Deposited: | 28 Aug 2014 10:18 |
Last Modified: | 26 Apr 2022 09:14 |
URI: | https://research.sabanciuniv.edu/id/eprint/24360 |