Şen, Halil and Bülbül, Kerem (2012) A simple, fast, and effective heuristic for the single-machine total weighted tardiness problem. In: 13th International Conference on Project Management and Scheduling (PMS 2012), Leuven, Belgium
PDF
TWT_nested_PMS2012_MainFile.pdf
Download (163kB)
TWT_nested_PMS2012_MainFile.pdf
Download (163kB)
Abstract
We consider the single-machine total weighted tardiness problem (TWT) where a set of n jobs with general weights w_1,…, w_n, integer processing times p_1,…, p_n, and integer due dates d_1,…, d_n has to be scheduled non-preemptively. If C_j is the completion time of job j then T_j = max(0, C_j - d_j) denotes the tardiness of this job. The objective is to find a schedule S^{*}_{WT} that minimizes the weighted sum of the tardiness costs of all jobs computed as \sum_{j=1}^{n} w_j T_j. This problem is known to be unary NP-hard. Our goal is to design a constructive heuristic for this problem that yields excellent feasible solutions in short computational times by exploiting the structural properties of a preemptive relaxation.
Item Type: | Papers in Conference Proceedings |
---|---|
Additional Information: | Halil received the 3rd place in the student paper competition. |
Uncontrolled Keywords: | Preemptive relaxation, transportation problem, nested schedule |
Subjects: | T Technology > T Technology (General) > T055.4-60.8 Industrial engineering. Management engineering T Technology > T Technology (General) > T055.4-60.8 Industrial engineering. Management engineering > T57.6-57.97 Operations research. Systems analysis |
Divisions: | Faculty of Engineering and Natural Sciences > Academic programs > Manufacturing Systems Eng. Faculty of Engineering and Natural Sciences |