Kılıç, Murat and Ulusoy, Gündüz and Sivrikaya Şerifoğlu, Funda (2008) A bi-objective genetic algorithm approach to risk mitigation in project scheduling. International Journal of Production Economics, 112 (issue ). pp. 202-216. ISSN 0925-5273
This is the latest version of this item.
PDF (Research paper)
Risk_IJPE_2008.pdf
Download (345kB)
Risk_IJPE_2008.pdf
Download (345kB)
Official URL: http://dx.doi.org/10.1016/j.ijpe.2006.08.027
Abstract
A problem of risk mitigation in project scheduling is formulated as a bi-objective optimization problem, where the expected makespan and the expected total cost are both to be minimized. The expected total cost is the sum of four cost components: overhead cost, activity execution cost, cost of reducing risks and penalty cost for tardiness. Risks for activities are predefined. For each risk at an activity, various levels are defined, which correspond to the results of different preventive measures. Only those risks with a probable impact on the duration of the related activity are considered here. Impacts of risks are not only accounted for through the expected makespan but are also translated into cost and thus have an impact on the expected total cost. An MIP model and a heuristic solution approach based on genetic algorithms (GAs) is proposed. The experiments conducted indicate that GAs provide a fast and effective solution approach to the problem. For smaller problems, the results obtained by the GA are very good. For larger problems, there is room for improvement.
Item Type: | Article |
---|---|
Uncontrolled Keywords: | project scheduling; risk; multiobjective optimization; genetic algorithms |
Divisions: | Faculty of Engineering and Natural Sciences |
Depositing User: | Gündüz Ulusoy |
Date Deposited: | 16 Dec 2008 15:18 |
Last Modified: | 22 Jul 2019 12:08 |
URI: | https://research.sabanciuniv.edu/id/eprint/10940 |
Available Versions of this Item
-
A bi-objective genetic algorithm approach to risk mitigation in project scheduling. (deposited 26 Dec 2006 02:00)
- A bi-objective genetic algorithm approach to risk mitigation in project scheduling. (deposited 16 Dec 2008 15:18) [Currently Displayed]