Şahin, Güvenç and Ahuja, Ravindra K. (2011) Single-machine scheduling with stepwise tardiness costs and release times. Journal of Industrial and Management Optimization, 7 (4). pp. 825-848. ISSN 1547-5816 (Print) 1553-166X (Online)
This is the latest version of this item.
PDF (This is a RoMEO green publisher -- author can archive pre-print (ie pre-refereeing))
StepwiseTardiness-YardOperations_SahinAhuja.pdf
Download (263kB)
StepwiseTardiness-YardOperations_SahinAhuja.pdf
Download (263kB)
Official URL: http://dx.doi.org/10.3934/jimo.2011.7.825
Abstract
We study a scheduling problem that belongs to the yard operations component of the railroad planning problems, namely the hump sequencing problem. The scheduling problem is characterized as a single-machine problem with stepwise tardiness cost objectives. This is a new scheduling criterion which is also relevant in the context of traditional machine scheduling problems. We produce complexity results that characterize some cases of the problem as pseudo-polynomially solvable. For the difficult-to-solve cases of the problem, we develop mathematical programming formulations, and propose heuristic algorithms. We test the formulations and heuristic algorithms on randomly generated single-machine scheduling problems and real-life datasets for the hump sequencing problem. Our experiments show promising results for both sets of problems.
Item Type: | Article |
---|---|
Uncontrolled Keywords: | Single-machine scheduling; stepwise tardiness; hump sequencing; railyards; yard operations |
Subjects: | T Technology > TF Railroad engineering and operation > TF501-668 Railway operation and management T Technology > T Technology (General) > T055.4-60.8 Industrial engineering. Management engineering > T57.6-57.97 Operations research. Systems analysis |
Divisions: | Faculty of Engineering and Natural Sciences Faculty of Engineering and Natural Sciences > Academic programs > Manufacturing Systems Eng. |
Depositing User: | Güvenç Şahin |
Date Deposited: | 27 Oct 2011 14:04 |
Last Modified: | 26 Apr 2022 08:49 |
URI: | https://research.sabanciuniv.edu/id/eprint/17312 |
Available Versions of this Item
-
Single-Machine Scheduling with Stepwise Tardiness Costs and Release Times. (deposited 31 Oct 2007 08:18)
-
Single-machine scheduling with stepwise tardiness costs and release times. (deposited 06 Dec 2010 16:38)
- Single-machine scheduling with stepwise tardiness costs and release times. (deposited 27 Oct 2011 14:04) [Currently Displayed]
-
Single-machine scheduling with stepwise tardiness costs and release times. (deposited 06 Dec 2010 16:38)