Dynamic resource constrained multi-project scheduling problem with weighted earliness/tardiness costsPamay, Mehmet Berke and Bülbül, Kerem and Ulusoy, Gündüz (2012) Dynamic resource constrained multi-project scheduling problem with weighted earliness/tardiness costs. In: Uzsoy, R. and Sarin, S. and Pulat, S., (eds.) Essays in Planning, Scheduling and Optimization: A Festschrift in Honor of Salah E. Elmaghraby. Springer, New York. (Accepted/In Press)
AbstractIn this study, a conceptual framework is given for the dynamic multi-project scheduling problem with weighted earliness/tardiness costs (DRCMPSPWET) and a mathematical programming formulation of the problem is provided. In DRCMPSPWET, a project arrives on top of an existing project portfolio and a due date has to be quoted for the new project while keeping the costs related to changes in the schedule at a minimum. The objective function consists of the weighted earliness tardiness costs of the activities of the existing projects in the current baseline schedule plus a term that increases linearly with the anticipated completion time of the new project. An iterated local search based approach is developed for large instances of this problem. In order to analyze the performance and behavior of the proposed method, a new multi-project data set is created by controlling the total number of activities, the due date tightness, the due date distribution, the number of resource types, and the completion time factor in an instance. A series of computational experiments are carried out to test the performance of the local search approach. Moreover, exact solutions are provided for the small instances. The results indicate that the local search heuristic performs well in terms of both solution quality and solution time.
Repository Staff Only: item control page |